Beginning Monday, May 4, crack sealing road work will begin in La Center. The road work is expected to last until Wednesday, May 6. Roads will be limited to single lane traffic with flaggers; delays are expected. Crack sealing will begin at approximately 8:30 a.m. and be completed by 3:00 p.m. Following crack sealing completion, pothole repair is expected to begin the following week on May 11.
Approximate crack sealing schedule:
Monday, May 4
8:30 a.m. – NW Timmen Road, E. Caples Ct. and E. 13th St
10:30 a.m. – NW La Center Rd.
2:00 p.m. – W 10th St
Tuesday, May 5
8:30 a.m. – E. Fir Ave, E. Pioneer Loop and E. Cedar Ave
Wednesday, May 6
8:30 a.m. – Misc. roads (areas missed)